Many Nairobi office projects sit inside managed commercial buildings with their own fit-out requirements. Those rules can affect partitions, ceilings, fire systems, HVAC, electrical loads, working hours, contractor access, material deliveries and the date a tenant is allowed to occupy. The landlord process should therefore be treated as part of the project programme, not as an administrative task added after design.

Before signing or finalising the premises

Request and review

  • Tenant or fit-out manual.
  • Base-building drawings and available services information.
  • Permitted electrical and cooling loads.
  • Fire and life-safety requirements.
  • Rules for wet services, core drilling and penetrations.
  • Working hours and noisy-work restrictions.
  • Loading-bay, goods-lift and delivery procedures.
  • Contractor registration, insurance and health-and-safety requirements.
  • Deposits, review fees and reinstatement obligations.

Design around the building rules

A floor plan can look resolved while still conflicting with sprinkler coverage, smoke detection, HVAC zoning, emergency egress, electrical distribution or ceiling access requirements. The design team should coordinate the tenant plan against the building information before the submission is treated as final.

What may form part of a landlord submission?

Requirements vary by building, but submissions can include layout drawings, reflected ceiling plans, power and data layouts, mechanical changes, fire-system modifications, material information, signage details, contractor documentation and a work programme. The project team should follow the specific building manual rather than assume one standard checklist applies everywhere.

Construction access can shape the programme

Restricted delivery hours, limited goods-lift bookings, noisy-work windows and shutdown approvals can make an apparently simple programme unrealistic. The contractor should plan around these constraints before the start date is promised.

Clarify landlord vs tenant interfaces

  • Who modifies and commissions base-building HVAC?
  • Who moves sprinkler heads or detectors?
  • Who approves electrical load increases?
  • Where can condensate, drainage or water connect?
  • Who controls access-control integration?
  • Who pays building review or supervision charges?
  • What must be reinstated at lease end?

Handover and permission to occupy

Some buildings require inspections, testing records, as-built information, clearance of outstanding defects or confirmation that landlord conditions have been met before allowing occupation. Build these tasks into the end of the programme rather than treating practical completion as the final administrative step.